4 hrs. cleaning and priming parts.

All deburred and cleaned and ready for priming.

Priming done, now gathering the parts for the Rib 2 assembly and the next step, which is the tail cone assembly.

NEXT TASKS:
  1. Rib 2 assembly.
  2. Tail cone assembly.
  3. Need to find the rudder and elevator guides for these assemblies as they weren't in the Rib assembly parts bags (I think I found them in the rudder cable bag - to be confirmed).
  4. Fill bottom rivets of elevator and fillet the composite tips of it to the skin (to be done in "spare" time).
  5. Rivet the one on the left wing's step rib that needs special handling.?? (to be done in "spare" time).

No comments: