Tuesday, March 15, 2016

2 hrs. riveting the bottom of the leading edge and fuel tank to the main spar.  Only 3 rivets remain on the bottom to be riveted, two near the pitot that I couldn't fit the rivet gun and another in which I need to shorten the rivet.


NEXT TASKS:
  1. Rivet the 3 bottom rivets that need special handling.  Also one on the step rib that needs special handling.
  2. Fill rivets with Bondo.
  3. Install landing lights.
  4. End rib installed (Jig needs to come off).
  5. Wing tip assembly riveted on and light installation.
  6. Composite filler for join between wing tip and skins. Perhaps other seams can use some filler?
  7. Put the aileron and flap on the wing to check for straightness of the trailing edge (Thanks Peter, I saw that on your blog! ;-)). Based on what I'm reading online it seems likely that I'll need to re-rivet some of the aileron/flaps to line up the trailing edges...  Wish I knew this before I had riveted them...
  8. Finish sanding of left wing bottom rivet heads.
  9. Finish right wing.
  10. Finally finish one of the composite tips of the elevator.
  11. Fill rivets of elevator with Bondo.
  12. START ON FUSELAGE!